SL NR. PROJECT / CONTRACT DESCRIPTIONS CONTRACTOR CONSULTANT / CLIENT PERIOD
1 PROPOSED CHEMICAL STORAGE WAREHOUSE AT INDUSTRIAL AREA STREET 47 GRP CHEMICAL STORAGE TANK SALAM PETROLEUM SERVICES W. L. L. Qatar Design Consortium 2019
2 RE AJ3387 KEPPEL SEGHER BIOGAS GRP EXTRACTION HOOD AND DUCTING ERG (AIR POLLUTION CONTROL) LTD.   2019
3 GRP VESSEL / GRP DUCTING & GRP VESSEL / DUCTING PIECES & PREFILTER ERG (AIR POLLUTION CONTROL) LTD.   2019
4 Veolia Water Technologies - Doha South Sewage Treatment Works GRP Vessels & GRP Ducting Arrangements ERG (AIR POLLUTION CONTROL) LTD.   2018
5 ISOLA DANA Upgrade OCU – Petroserv Ltd GRP Vessels & GRP Carbon Filter ERG (AIR POLLUTION CONTROL) LTD.   2018
6 PETROSERV - 8 UNITS + PS 37 GRP VESSEL IPEC NV PETROSERV 2018
7 New Hamad Port Project Mesaieed (16DB-DVC) SUPPLY OF GRP VESSELS INTERNATIONAL CONCEPT MANAGEMENT   2018
8 PR# 7922 DEODERIZER VESSEL DEODERIZER VESSEL QD-SBG GROUP Hamad International Airport 2018
9 GRP HOLDING HCL TANK GRP HOLDING HCL TANK AQUA CHEMIE DMCC   2018
10 Roads Infrastructure in Govt. Residential Area in North of Al Wukair GRP Ducting Arrangement AA Engineering Services   2017
11 Refurbishment and Upgrading Works for Varoius Sewage Pumping Stations GRP Ducting GEC Contracting Services & Trading (Abdulla Al Nass Group)   2017
12 CP08-A-1: Infrastructure & Landscaping at Spine and Marina Roads & Deodorizer Vessels Of Varoius Sizes Al Raida Engineering & Industrial Services   2017
13 ASPIRE Polishing Plant BACK Wash Water Tank (7400L x 3600W x 3000 H) BRINE Mixing Tank (6200L x 3600W x 3400 H) NEUTRALIZED Water Tank (6500L x 3600W x 3000 H) DEGREMONT SAS ASPIRE ZONE 2016
14 UNIT-82: REPLACEMENT OF TANK : 82-Y001-YT002 FRP Dehydrogen & Chlorination Tank DOPET RASGAS 2016
15 EPCM & CONSTRUCTION CONTRACT FOR PLANT CHANGES, MINOR BASE & MEDIUM PROJECTS- P-810122 FIELD FACILITIES POTABLE WATER BUFFER TANK Size: Ø3000 x 8850 QATAR KENTZ WLL QATAR SHELL GTL LIMITED 2016
16 Refurbishment & upgrading works for various Pumping Stations (Phase -8 ) Project No. C729/2 GRP Ducting Arrangement Petroserv Ltd   2016
17 Water Treatment Plant of EF5 Project GRP Chemical Storage Tank ( Hydrex 2209) Kobelco Eco Solution – Qatar Steel Kobelco Japan 2014
18 AS SAMRA EXPANSION - WASTE WATER TREATMENT PLANT GRP OCU SCRUBBING TOWERS Caustic Soda Storage tank Sodium Hypochlorite Storage Tank Sodium Hypochlorite Storage Tank DEGREMONT SAS THE HASHEMITE KINGDOM OF JORDAN 2013
19 Doha West STP Extension Ph III Raw Sewage Storage Tank 60m3 - 4.0m dia x 5.0m ht. Degremont S.A Nippon Koei Co. Ltd. 2012
20 U.A.E. GRP Vent Master(0.65m Diax2.0m Ht. with butterfly damper) Ashbrook Simon-Hartley,U.K. Eagle Electromechanical, Abudhabi 2012
21 U.A.E. GRP Vent Master(0.5m Diax1.8m Ht. with butterfly damper) Ashbrook Simon-Hartley,U.K. Eagle Electromechanical, Abudhabi 2012
22 CP 729/2 - Petroserv/ Eastern Trdg. & Cont GRP Deodoriser Vessels(3.0m Diax3.4m Ht. with Pre-filters and butterfly damper) Ashbrook Simon-Hartley,U.K. Petroserv/ Eastern Trdg. & Cont 2012
23 Shell GTL Plant GRP Lime Silo(1.5m Diax3.4m Ht. with steel access platform & ladder) Aqua Chemie, U.A.E Shell GTL 2012
24 Barwa City Scrubber Towers 1.9 mtr Dia X 6.19 - 2 nrs Degremont - BUTEC Degremont S.A 2011
25 Barwa City Caustic soda GRP storage tank 3 m3 - 1. Sodium hypochlorite GRP tank 25 m3 - 2. Ferric chloride GRP tank 25 m3 - 1 Consortium Degremont - BUTEC Degremont S.A 2011
26 Qatar Fertiliser Co (SAQ) GRP WASTE WATER STORAGE TANKS 100 m3-4500mm diax6250mm ht-2 nrs. 50 m3-3500mm diax5200mm ht.-2 Nrs. 20 m3-3000mm diax3200 mm ht.-1Nr QAFCO QAFCO 2010
27 Qatar Petroleum Double walled Foam Storage tank Thompson Specialities   2010
28 QATALUM GRP Demineralization Water Storage Tanks Al Jaber Engg. SNC Lavalin 2009
29 Emirates Aluminium Smelter, Abudhabi GRP Double Walled Degas & Shock Storage Tank (66.0m3) 3.3m dia x 7.5m ht. with ladder, handrailing & platform Siemens Water Technologies, USA SNC Lavalin/ Worley Parsons 2009
30 Dubai Sports City, U.A.E. GRP Deodoriser Vessels(3.0m Diax3.4m Ht. 1.2m Diax2.6m Ht. & 0.85m Diax2.0m Ht.) Centriquip,U.K. Eagle Electromechanical, Abudhabi 2008
31 Barwa Housing Project GRP Deodoriser Vessels(0.85m Diax2.0m Ht.) Centriquip ,U.K./ Eastern Trading Public Works Authority(Ashghal) 2008
32 Doha West Sewage GRP Ventilation & Extract Ducting Degremont Suez Nippon Koei Co. Ltd. 2008
33 Lusail Development GRP Dampers(150mm dia - 600mm dia) Degremont Suez Degremont Suez 2008
34 QAFCO Laboratory GRP Fume Cupboard Ducting Marine Airconditioning & Refrigeration Co. QAFCO 2008
35 Civil Project 617 Pumping Station GRP Ventilation & Extract Ducting with stack(0.8m x 5.0m) Kubota Corporation Parsons Consultants 2008
36 Palm Jumeirah, U.A.E GRP Vertical Storage Vessels for highly corrosive chemicals (3.2m dia x 6.5m ht-5nrs, 2.4m dia x 5.8m ht-1nr,3.0m dia x 3.8m ht-1nr,3.0m dia x 2.25m ht-1nr, 3.0m dia x 4.5m ht-1nr,1.6m dia x 3.2m ht-1nr) Suez Environment- Degremont-Besix JV KEO International 2008
37 Salalah Methanol Plant, Oman GRP Degas & Shock Storage Tank(5.0m3) with ladder, handrailing & platform Siemens Water Technologies, USA Daewoo E & C 2008
38 Project in U.A.E. GRP Deodoriser Vessels(3.0m Diax3.4m Ht. 1.4m Diax2.6m Ht. & 1.2m Diax2.4m Ht.) Centriquip,U.K. Al Komed Engg., Bahrain 2007
39 CP 361 GRP Screw Pump Covers ITT Sanitaire Europe Hyder Consulting 2007
40 Doha West Sewage Treatment Plant Biological & Chemical Deodourizers(3.9m dia x 8.0m Ht.-2 nrs. & 3.8m dia x 3.2m Ht.-1 nr.) Degremont Suez Nippon Koei Co. Ltd 2007
41 Project in U.A.E. GRP Deodoriser Vessels(3.0m Diax3.4m Ht. 1.4m Diax2.6m Ht. & 1.2m Diax2.4m Ht.) Centriquip,U.K. Eagle Electromechanical, Abudhabi 2007
42 Lusail Development GRP Discharge Stack(1.4m dia x 15.5m Ht.) Degremont Suez Hyder Consulting 2007
43 Ras Laffan Power Plant GRP Lining to Holding Tank Larsen & Toubro Qatar Ras Laffan Power Company 2006
44 Museum of Islamic Arts GRP Lining to Holding Tank Baytur/Mercury Public Works Authority(Ashghal) 2006
45 Rasgas Off spec Pond Facility GRP Horizontal Storage Vessels for special products Qatar Kentz Rasgas 2006
46 Nuovo Pignone Gas Turbine Service Facility GRP Vertical Storage Vessels for special Turbine Oil Nuovo Pignone/ Qatar Kentz Nuovo Pignone 2006
47 Dukhan Consolidated Camp Facilities GRP Deodoriser Vessels(1.2m Diax1.8m Ht.- 1 nr. & 1.6m Diax2.15m Ht. - 1 nr.) Centriquip U.K. Qatar Petroleum 2005
48 Project in U.A.E. GRP Deodoriser Vessels(1.6m Diax2.15m Ht.- 1 nr. ) Centriquip U.K. Dubai Electricity & Water Company 2005
49 Project in Bahrain 300m3 RO Plant GRP Degassifier and Buffer Tank Celar Water Eqpt., Dubai   2005
50 Ras Laffan Power Plant GRP Settlement & Treatment Tank Qatar Technical Support Ras Laffan Power Company 2005
51 Qatargas Expansion Trains 3 & 4 GRP Lining to Holding Tank Consolidated Contr. Int'l Co.(CCIC) Qatargas 2005
52 CP M 631 GRP Covers to Inlet Chambers Lotus Trdg. & Contr. KEO International 2004
53 CP 623 GRP Ventilation & Extract Ducting with stack(0.9m dia x 9.0m Ht.) Danway Qatar ASCO 2004
54 Salwa & Immigration Interchange GRP Ventilation & Extract Ducting with stack(1.4m dia x 10.0m Ht.), kiosk AA Eng. Services High-Point Rendel 2004
55 CP 379/4 GRP Domed Covers to Inlet Works, Baffle Boards & Weir Plates AA Eng. Services KEO International 2004
56 CP 379/4 GRP Lining to Mild Steel Ballast in Aeration Tanks AA Eng. Services KEO International 2004
57 CP 256/2 GRP Ventilation & Extract Ducting with stack(0.4m dia x 12.5m Ht.) Danway Qatar Maunsell 2004
58 Upgrading of Jetty Services GRP Deodoriser Vessels(1.0m Diax1.8m Ht.- 2 nrs. & 1.2m Diax1.8m Ht. - 1 nr.) Centriquip,U.K. Emiri Navy - Technical Office 2004
59 Sea line Beach Resort GRP Treated Effluent Storage Tank - Size : 8.5m Dia x 2.0m Ht. With cover Danway Qatar QNH – Technical Office 2004
60 Dukhan Sewage Treatment Plant GRP liners/lining, ladders to manholes, Tanks, Ladders, Handrailing & Gratings to STP Petroserv Ltd. QP 2003
61 Project M 630 GRP Deodorizer Vessels(3.0m Diax3.4m Ht.) GRP Pre-Filter Units with louver dampers CPL Environmental Eng. U.K. Hyder Consulting 2003
62 CP 528 GRP ladders, Handrailing & grating to Pumping Station & Surge Vessel HBK Contr. Co. Hyder Consulting 2003
63 CP 528 GRP Ventilation & Extract Ducting with stack(1.0m dia x 11.5m Ht.) Danway Qatar Hyder Consulting 2003
64 CP 586 GRP ladders, Handrailing & grating(GRP & SS) to Pumping Station & Surge Vessel Chamber Tadmur Contr. & Trading KAME 2003
65 CP 393 GRP Tanks, ladders, Gratings, handrailing, sealing plates to Aerobic Digester Tank, Equalisation Tank, Effluent Storage Tank, Pre-aeration Tank, Septage Reception Tank, Toxic Sewage Holding Tank, Tanker Discharge Channels, Works Pumping Station, Inlet Works, Distribution Chambers, Works Return Pumping Station. Razak Contr. KAME 2002
66 US Army Base GRP Preformed Lifting Station Basins for wet well & Valve Chambers How United Services US Army Corps 2002